Project Startup | Midstream - Processing Plant
Tidewater's Pipestone Montney Processing Plant Put in Service
Tidewater Midstream and Infrastructure Ltd. reported the start-up of the Pipestone Montney, sour deep-cut gas processing complex.
Click here to access the project in Shale Expert's Infrastructure Database
The Pipestone Gas Plant is designed to process approximately 100 MMcf/day of sour gas and includes an acid gas injection well, salt water disposal well, and pipelines that directly connect to Tidewater’s Pipestone Gas Storage Facility. Additionally, the Pipestone Gas Plant is connected to both the Alliance and TC Energy pipeline network.
The Pipestone Gas Plant began processing sour gas on September 15, 2019 and is currently processing approximately 30 MMcf/day of sour gas during this start-up phase. Tidewater expects processing to ramp up to at or near full capacity of 100MMcf/day by the end of the year.
Related Categories :
Project Startup
More Project Startup News
-
Keyera, Ovintiv Start Up Montney Pipestone Processing Complex
-
Kinder Morgan, EIG Put Final Stage of Elba LNG Expansion In-Service
-
Elevation Midstream IDs 2020 Budget; Puts Badger Gathering Facility Online
-
EPIC Pipeline Marks First Permian Crude Shipment
-
Trafigura Begins Permian Crude Shipments; Two More Pipeline Startups Imminent
Canada News >>>
-
Western Canada Upstream M&A: Q1 2026 Transaction Report

-
Canadan E&P 2026 Program Calls for 448 Net Wells, Up 24% vs. 2025 Plan -

-
EIA’s “Glut” Calls: The 2025 Surplus Claim — and How 2021–2024 Forecasts Actually Held Up

-
Whitecap Details 2026 Duvernay & Montney Program

-
ARC Resources: Lower 2026 Capex, Higher Volumes






