Phillips 66 said it is taking the following steps
In Midstream, the Red Oak Pipeline and Sweeny Frac 4 projects, as well as Phillips 66 Partners’ Liberty Pipeline, will all be deferred.
The Red Oak Pipeline had a initial startup of 1H 2021 and its own 50% by Phillips
The Liberty Pipeline also had a initial startup date of 1H 2021.
Source : Phillips 66 via Shale Experts Presentation Database
The company is taking the following actions:
- Reducing 2020 consolidated capital spending by $700 million to $3.1 billion.
- Capital spending is now expected to be $3.0 billion. This reduction in adjusted capital from the $3.3 billion budget reflects a $700 million reduction in our consolidated capital spending, partially offset by a $400 million reduction in cash capital contributions anticipated from DCP Midstream.
- Reducing operating and administrative costs by $500 million in 2020.
- Temporarily suspended share repurchases effective March 18. Share repurchases during the first quarter of 2020 were approximately $440 million. Phillips 66 will evaluate timing to resume share repurchases.
- Secured a new $1 billion, 364-day term loan facility. This facility provides additional liquidity and financial flexibility in addition to the existing $5 billion revolving credit facility. Phillips 66 Partners has a $750 million revolving credit facility.
Related Categories :
Pipeline Project Update
More Pipeline Project Update News
-
TC Energy Pulls the Plug on the Keystone XL Pipeline
-
Summit Midstream Gets FERC Approval for Double E Pipeline
-
FERC Approves Double E Pipeline; Permian Basin
-
EPIC Crude Oil Pipeline Put in Service
-
Crestwood Announces Fourth Quarter 2019 Results
Permian News >>>
-
Why $90 Oil Isn’t Bringing Back the Rigs -

-
These Three Companies Will Increase Drilling & Completion Over The Next 3 Year -

-
Q1 A&D Transactions Jump to $30B , While Deal Flow Was Down 40%

-
Wright to U.S. Oil Industry: The Price Signal Is Telling You to Drill

-
Apa Corp : Doing More With Less